Sully to Cosmeston Active Travel Phase 2 logoSully to Cosmeston Active Travel Phase 2

Milestones

  • Active Travel Funding approved

    April 2021

     

    -

     

    March 2022

    Welsh Government agree funding for design and feasibility of an active travel route connecting Sully and Cosmeston.
  • Route option consultation

    February 2022

     

    -

     

    March 2022

    Public asked which route option they would prefer the Council to design.
  • Route design

    April 2022

     

    -

     

    January 2023

    Arcadis Consultancy design active travel route based on consultation responses.
  • Consultation on concept design

    April 2023

     

    -

     

    May 2023

    Gather thoughts on the Councils active travel route.
  • Apply for funding to complete detailed design

    January 2024

     

    -

     

    March 2024

    Subject to approval, the Council would apply for Welsh Government Active Travel funding to complete the detailed design of the route.
  • Consultation on final design

    December 2024

     

    -

     

    January 2025

    If funding is agreed for detailed design, then this phase would be for public consultation on final design.